MASSEY CLUSTER – RELOCATION OVERVIEW

Project Overview:

The Massey Cluster became the largest relocation programme TROW Group has undertaken in a single area, with 12 homes successfully relocated following the Auckland storm and flood events.

These were not empty buildings or simple structures waiting to be moved. Each home had belonged to a family, carried years of memories and represented a place people had called home before Cyclone Gabrielle changed that. With the properties red-stickered and no longer able to be lived in, relocation provided an opportunity to give these homes another life rather than seeing them demolished and sent to landfill.

Relocating an entire house also comes with a very different set of environmental benefits. Instead of breaking a home down into hundreds of individual components and processing or disposing of the resulting materials, relocation allows a much greater portion of the existing structure to remain intact and continue serving a purpose elsewhere. This reduces the demand for new building materials, avoids unnecessary waste and keeps the embodied energy already invested in the homes in use for longer.

Completing 12 relocations within the same area required significant coordination between our project teams, transport operators, traffic management, property owners, councils and the wider community.

Completing 12 relocations within the same area required significant coordination between our project teams, transport operators, traffic management, property owners, councils and the wider community. Moving a house through an established neighbourhood can have a real impact on surrounding residents, so minimising disruption was a key part of the planning from the beginning.

Where possible, relocations were scheduled for quieter periods, including late-night or early-morning movements, helping to reduce traffic impacts and avoid unnecessary congestion. Courtesy letters were also delivered to neighbouring properties ahead of movements, giving residents notice of what was happening, when to expect it and what temporary disruptions they might experience.

Health and safety remained at the centre of every relocation. Each move required detailed planning around the condition and structure of the house, lifting and transport requirements, overhead services, 

traffic movements, access routes and the safety of our teams and the public. Every relocation presented its own set of considerations, meaning the process was carefully assessed rather than treated as a one-size-fits-all operation.

For the TROW team, the Massey Cluster demonstrated what can be achieved when relocation, recovery and resource recovery are considered together. Twelve homes that had been written off after the cyclone were given another opportunity to be used, while reducing the amount of material entering the waste stream and supporting a more circular approach to disaster recovery.

It was also a reminder that recovery is about more than moving buildings. It is about handling people’s homes, possessions and circumstances with care, while finding practical ways to reduce the environmental impact of rebuilding after a disaster.

Project Highlights

A note on our relocation figures

When we relocate a house, the house itself isn’t included in the waste recovery tonnage below. That’s because the entire structure has been retained and moved for continued use, rather than being processed as demolition waste.

The figures instead capture the materials generated around the relocation process, including materials removed during preparation and associated site works. These materials are then tracked through reuse, recycling, hardfill and landfill.

So while the relocated house represents a significant form of reuse in its own right, it isn’t counted within the tonnage table. The table measures the recovery of materials generated during the relocation works, not the weight of the house itself.

38 Clover Drive, Massey

37 Clover Drive, Massey

8 Lincoln Garden Close, Massey

14 Clover Drive, Massey

Remaining 8 Relocations

10 Clover Drive, Massey

16 Clover Drive, Massey

20 Clover Drive, Massey

24 Clover Drive, Massey

26 Clover Drive, Massey

32 Clover Drive, Massey

34 Clover Drive, Massey

36 Clover Drive, Massey